Sanjeev Kumar General Secretary of RWA, sector 51 informing to the Project Engineer of WC-3 that during resurfacing of slip/service road of sector 51 by the contractor without removing the building material/malbar like big slabs, Big size Iron and RCC pipes and other best construction material from the site.
He also clame that the road is not straight and proper as breadth of the road/size is varing due to slabs and other waste material on the site as shown in photos.
He requested for early removal of the waste construction /builging material between gate number 7 to gate number- 8 of sector-51, before second and final layer of damer during resurfacing work of service road (towards sector 72, side) and reconstruction of divider between main road and service road (opposite to gate number- 8 of sector 51).
As you see the photos dated 3-3-2019 before resurfacing of the road. At that time contractor of the road had not removed the waste construction material/waste building material and other dumping material/waste from the site.
There were many waste RCC pipe, cast iron pipes, big waste slabs and other construction materials which had to be removed from the site before resurfacing of the road.
As you can see in the photo that contractor had not removed the slab and road became narrow at that particular point.
On 9-4-2019 we requested to Sri Ritwick ji junior engineer from work circle 3 who is incharge of construction of this road and requested him to remove all these malbas before top layer of butmin/black damber road is put.
Representative of our RWA Shri Neeraj Kapoor ji personally met with Shri Ritwick Ji on the site & he assured us to do the same before final layer resurfacing.
During the visit representative of sector 51,also requested for reconstruction of the divider just opposite to gate number – 8 of sector-51 which was broken by management of Manav Rachna School.
Sanjeev Kumar
General Secretary